There’s a quarter century of tradition behind Dynasty Court’s...
2010-03-23
Mike Baños
Kapihan
Energy exec warns: Be Prepared to pay 3X more for electricity
By Mike Baños
IfMalacañang’s quick fix solution for the power
crisis in Mindanao pushes through, consumers could pay as much as three times
what they’re now paying for electricity.
“Should
there be no solution forthcoming from the National Power Corporation (Napocor)
or the Private Sector Asset and Liabilities Management Corp. (PSALM) within the
next few weeks, utilities like us will be forced to contract out for diesel
driven generators,” said Engr. David A. Tauli, senior vice president for
engineering of the Cagayan Electric Power and Light Company (Cepalco) during a
presentation on the Mindanao Power Crisis to members of the Rotary Club of
Cagayan de Oro Centerpoint Friday evening.
However,
Tauli cautioned that should this happen, Cepalco customers would pay as much as
three times as much as their present power rate.
“Assuming
a 50 percent curtailment, you would pay at least P7.50 per kilowatt hour (kWh)
if the additional power would come from non-Napocor source,” Tauli said.
He
noted that Napocor is compelled by law to stick to its approved power rates and
could thus not be in a position to impose rate increases.
Cepalco exec David Tauli interacts with RC Cagayan de Oro Centerpoint Corp. Sec. Susan delas Alas during the open forum of his presentation on the Mindanao Power Crisis.
The
energy executive maintains there are six projects the Napocor and PSALM can do without
forcing themselves or their customers to pay astronomical power rates under the
planned emergency measures the government is considering with the use of
calamity funds and the President’s emergency power.
“We
really don’t need emergency powers or a state of calamity to address the
present power crisis if only Napocor and PSALM immediately implement six key
projects which would restore the Mindanao Grid’s capability to deliver the
contracted demand to all their customers,” he added.
Of
the six, Tauli noted that while Napocor and PSALM have committed to putting the
Iligan Diesel Power Plant onstream with 108 megawatts (MW) and dredging the
forebay of the Pulangi IV hydroelectric power complex in Bukidnon to increase
its peaking capability from the current 85 to 255MW, the two firms have been
slow in implementing the measures.
Other
options Napocor and PSALM could do immediately are to operate Power Barges 117
and 118 as baseload power plants (rather than as a supplier of ancillary
services to the National Grid Corporation of the Philippines or NGCP), to
enable them to supply as much an additional 200MW to the Grid, without
excessive costs; dredge the Balo-i Plains to enable the Agus 2 HEPP to deliver
its full rated capability of 180 MW (from its current dependable capability of
only 60 MW) and to rehabilitatevarious
hydroelectric power plants on the Agus River to restore the power plants to
their full capability.
Only
when these measures have been fully implemented by Napocor and PSALM and there
still remains a power deficit should government deploy the expensive modular
generators, Tauli noted.
In
his March 19 column in a national business broadsheet, Ateneo de Manila
Professor Dean dela Paz estimates the modular gensets would require a “monthly operating expense of P2.5 billion against the
estimates of business losses of P1 billion from revenues forgone and
incremental expenses from self-generating units. If P2.5 billion includes fuel
and operation and maintenance (O&M) charges, the unsubsidized fuel cost
soars jumps from P19.60 to over P24.11 per kilowatt-hour (kWh) or higher.”
A
former consultant for Energy Affairs of the Joint Congressional Power
Commission and the Department of Justice inter-agency committee to review the
IPP Contracts, de la Paz said that based on Napocor’s
Small Utilities Group (Spug) dela Paz says the emergency funds must cover
leasing, O&M and fuel costs. He notes that modulars run on more expensive
fuel, while there are now four mothballed 242-MW power barges moored off
Navotas which run on less expensive bunker fuel.
Similarly,
activist-writer-researcher Arnold Padilla notes how government’s plan to lease
modular generation sets to produce an
additional 160 MW of electricity in Mindanao would require millions of liters
of diesel fuel.
For example,
the one (1) MW Mitsubishi Generac Diesel
Power Module consumes 238.56 liters per hour of diesel at 100
percent capacity, 187.92 liters at 75 percent, and 119.28 liters at 50 percent .
“If a 1-MW generator runs for the entire day, the extra cost would be
P46,490.57. If the entire 160 MW is generated in a day, the figure would be
P7.44 million. For one month (30 days), the overpricing would be P223.15
million. If the 160-MW generators were commissioned for three months (April to
June), taxpayers will shell out around P669.45 million on top of the real price
of diesel and the cost of leasing the generating plants,” Padilla noted in his
website.
Tauli
said the full implementation of the six projects would considerably reduce the
power shortfall by as much as 560 MW, in effect negating the need for the
modular gensets.
In his blog, dela Paz concurs that “workable
solutions” including tapping the four Navotas 242 megawatt barges and
transition supply contracts for two privatized 100 megawatt barges in each of
Nasipit, Agusan and Davao.
“There was enough time to settle tax issues over the 35 megawatt facility in
Iligan, dispatch peak power from a total of 56 megawatts from embedded private
generators and dredge the silted Pulangui Lake thus upgrading 87 megawatts to
at least 200 megawatts,” de la Paz said.
“Sans the dredging, these total at least 533 megawatts currently feasible and
enough to prevent 8 to 24 hour outages. These do not require corruption-prone
emergency powers that offer monetary windfalls for middlemen,” he added.